Line

Quantity Surveyor

For over 25 years, our business’s core discipline is Quantity Surveying, providing specialised construction economics services throughout a project’s life cycle. Our reporting standards set an industry benchmark and have been developed over years of auditing projects for some of the country’s largest financiers, industry peers, and regulators. As a trusted and respected panel member of many financial institutions of Australia, our independent advice on construction risks is relied upon for hundreds of new development projects each year. 

Pre-Construction

Feasibility Studies

A feasibility study assesses the viability of a project for the developer to determine the profitability of a project at a minimal cost. Using basic dimensioned sketches and industry experience, we can produce the initial development costs to enable the decision making process at the early stages.

Council Cost Reports

This report is prepared for the sole purpose of providing a proposed cost of development to accompany the DA submission to the consent authority to enable to provision of the Section 7.12 levy (formerly section 94A levy) in accordance with Clause 25J Section 7.12 levy of the Environmental Planning and Assessment Regulation 2000. Find out more here.

Dilapidation Reports

Often a requirement of any development consent, a dilapidation report is carried out prior to construction and following project completion. It reports on the condition of the neighbouring and council property so that any issues which arise as a result of the neighbouring construction works, can be easily identified. This assists, in the worst case, with dispute resolution.

Gross Floor Area Validation Reports

This report is often a requirement of the development application to verify the reliability and truthfulness of the areas provided on the drawings. This process allows for an independent, impartial and thorough assessment of the proposed project and its compliance with the requirements of floor space ratio and gross floor areas.

Head Contract Selection and Drafting of the Special Conditions

Quantity Surveyors are experts in drafting construction contracts. As such, our expertise can help the owner understand the often confusing and overwhelming process of contract selection. Following contract selection, we can draft the contract conditions and special conditions ready for tender.

Construction Programming

With our detailed knowledge of construction techniques and technology, we can create and manage a construction programme in the form of an easy to read Gantt chart. This outlines the task names, durations, start and end dates, predecessors and critical path, in line with the project financier’s delivery milestone dates, builders forecast and developer’s objectives.

Construction Finance Initial Reports

This report is a mandatory requirement of all project financiers of an owner to instruct a QS to assess the project and submit a formal report prior to bank funding approval. This includes creating an independent QS budget, reviewing the development application, architectural drawings, contract conditions, insurances, consultants’ reports and professional indemnity insurance levels, pre-sales and lease agreements amongst other requirements, and making comments and recommendations where required. Find out more here.

Construction

Progress Drawdown Reports

These reports are a mandatory requirement of all project financiers of an owner to instruct a QS on a minimum monthly basis to certify the value of works on a cost to complete basis. The report will also vet the essential project information, including but not limited to the construction program, project documentation such as boundary check surveys, structural engineer certificates, construction certificates, insurances, consultants professional indemnity insurances, unfixed plant and material, pre-sales and lease agreements amongst other requirements, and make comments and recommendations. Find out more here.

Variation Assessment Control

Any changes to the head contract between the client and the builder may lead to a variation of the Head Contract, and can either have a positive or a negative impact to the project and contract sum. Our office assesses any variation changes and advises with regards to the cost implications.

Strata Building Bond and Inspections Scheme

The Strata Building Bond and Inspections Scheme now requires the developer of new strata buildings that are 4 storeys or higher to pay a strata building bond, prior to obtaining occupation certificate. There are 8 stages to comply with this scheme and many of them involve a quantity surveyor. Find out more here.

Expert Witness Reports

At any stage of a project, if a developer finds that they are in dispute with their head contractor, then we are able to provide an Expert Witness Report to support any claims to be presented during litigation. We are on the Panel of AIQS Expert Witnesses and are suitably qualified and experienced in providing impartial and thorough assessments of construction costs at any stage of the project.

Post Occupancy 

Tax Depreciations Reports

The report is to estimate the depreciation and associated tax allowances that may be available to the owner under the Income Tax Assessment Act 1997 (ITAA97), Division 40 (plant and equipment) and Division 43 (capital works). It may be used to enable property investors to determine the deductible portion of the original costs of plant, equipment, and capital works on their investment property in each financial year over forty (40) years of ownership. Find out more here.

Building Defect Reports

Building defects are common at any stage of a building life cycle. They are often attributed to inefficient or incorrect construction details at the time of construction, and the symptoms can often take years or just months to appear. We provide defect identification, rectification recommendations, and associated construction costings in our reporting, so that owners understand the full scope of works and can actively plan for improvements.

Pre-Purchase Inspections

Prior to purchasing your own home, or next investment, it is a good idea to seek a professional to inspect the building and surrounding exterior grounds to assess their condition and identify any potential defects or wear and tear. Our reports identify potential issues and provide the costs to rectify such issues, so that the buyer understands the full picture prior to investing.

Asset Management Plans for Retirement Villages

As of July 1st 2021, new legislation was introduced to the Retirement Villages Act 2017 that requires all retirement villages located in NSW to prepare and make available to their residents’ an Asset Management Plan. The plan is prepared for a 10 year period must be prepared by an independent quantity surveyor or the auditor of the village whose appointment was consented by the residents, and contains the following four components:

  1. Asset Management Plan
  2. Asset Register
  3. Maintenance Schedule
  4. 3-year Report

Archi-QS can help you comply with the reforms to the Act, by either creating or auditing a pre-exiting asset management plan.

Send us a message

13 + 10 =